Delivery

The 30/60/90 pilot plan

What happens between "yes, let us pilot" and the renewal decision, with the shared activities the customer owns as well as the ones we do.

A pilot runs three months. Solution Architect is accountable for onboarding enablement: demos, platform setup and getting the customer's team working in the product. Customer Success owns the relationship and every communication. Product is accountable for adoption, meaning whether it sticks after SA has enabled them.

Use this as the shared plan with the customer. CS sends it in week one and runs the review at each checkpoint. For the full ownership matrix and the end-to-end flow, see Process & Timeline.

OwnersSolution ArchitectProductCustomer SuccessCustomer

The shape

W1W2W3W4W5W6W7W8W9W10W11W12W13Solution ArchitectProductCustomer SuccessCustomerAccess + co…Brand Brain buildPlatform setup + configDemos + onboarding enablementRequirements, months 1 to 2Onboarding …Analytics dashboardAdoption watch + interventionOutcome evidenceRelationship, weekly call, all comms, 30 / 60 / 90 reviewsClient-lane inputsSign off gr…Daily use, feedbackInternal validationBrand Brain liveDay 30Day 60, scope freezeDay 90
Solution ArchitectProductCustomer SuccessCustomerSalesScroll sideways to see the full 13 weeks.

Week 0: before the clock starts

Nothing below begins until these are true. Full list in the Onboarding SOPs.

Paid POC signed
Sales

With a written success criterion, not a free trial. This is the handover artefact.

Scope in their units
Sales

Masters and adaptations for creative, channels for ORM, accounts for paid. Not credits.

SPOCs named
CS

CS is our single point of contact. One SPOC customer-side plus an escalation contact, and the weekly call in the diary.

Security pack sent
SA

If their IT gates access. Longest pole in enterprise, so start it now.

Handover call held
Sales to CS

Sales walks CS, Product and SA through the problem statement and the success criterion. CS owns the relationship from here.

Access requested
SA specifies, CS asks

Platform, ad accounts, social handles, CRM. SA says what is needed; CS is the one who asks the customer.


Weeks 1 and 2: Brand Brain, every module

Brand Brain is built in the first two weeks, always

Every agent reads the graph before it acts, so nothing else can start properly until it exists. Two weeks is the target from the day client inputs land. The three lanes run in parallel and the client lane is the critical path, which is why the request list goes out on day one.

  1. Day 1Client-lane request list sentSolution Architect

    Brand guidelines, legal-approved disclaimers, negative keywords, product assets, layered sub-brand and platform rules, escalation matrix.

  2. Days 1 to 5Crawl lane runs, zero client effortSolution Architect

    Products, descriptions, CTAs, published rates, disclaimers as a seed, competitor set and their ads, review and marketplace sources.

  3. Days 3 to 8Hybrid lane drafted for validationSolution Architect

    Brand voice, personas, content angles and claim boundaries. We draft, the client corrects.

  4. Days 8 to 12Sources connected and freshness verifiedSolution Architect

    No stale feeds before go-live. This is visible on the Sources screen.

  5. Days 10 to 14Calibration outputs reviewed with the clientProduct + SA

    Against their own rulebook. Skills created for anything the defaults keep missing.

  6. End of week 2Client signs off the graphCustomer Success

    Recorded. This is the gate into module configuration.

Exit criteria: graph signed off, sources fresh, calibration accepted, refresh cadence agreed.

Built in parallel, so CS can run the account

Onboarding tracker
Week 1 · PM + SA

Every task with owner, status, blocker and target date. CS answers 'where are we?' from this, without asking anyone.

Product analytics dashboard
By end of month 1 · PM + SA

Actives against seats, surfaces opened, work created, goal movement, usage against estimate. CS spots a stalling account in week three.

If any of these slip past week two, escalate rather than starting module work on a half-built graph.


Weeks 3 to 12: the module tracks

Run only the tracks the customer bought. Each has its own first wow moment, and hitting that moment early is what carries the pilot.

AI Designer

  1. Week 3ConfigureSolution Architect

    Approval flows mirroring their sign-off chain, compliance rule packs, in-scope apps, Library folders per sub-brand.

  2. Week 3Wow moment: first real campaign setSolution Architect

    One master in, the full adaptation set out, inside a day. This is the moment that sells the pilot internally.

  3. Weeks 4 to 6Volume through the real workflowSolution Architect

    Brief, generate, Compliance Checker, Approvals, Library. Restate in writing that iterations do not count against the cap.

  4. Weeks 6 to 10Localisation and placement breadthProduct + SA

    Second language, second platform, marketplace or print if in scope.

  5. Weeks 10 to 12Throughput and cycle-time evidenceProduct

    Activity screen numbers against the week-1 baseline.

Brand Moderator

  1. Week 3Collect and configureSolution Architect

    Tone guide, approved templates, escalation matrix, complaint taxonomy, privacy masking, blocklist. CRM or ticketing connected.

  2. Week 4Shadow mode, one full weekProduct + SA

    Non-negotiable. The agent drafts, humans approve everything, nothing auto-posts. This is what catches appreciation comments creating tickets.

  3. Week 5Wow moment: a day cleared to zeroSolution Architect

    The queue emptied inside the SLA with drafted replies. The community team feels it immediately.

  4. Weeks 6 to 10Calibrate and expand channelsProduct + SA

    Feed rejections back into rules and playbook. Add channels from the agreed list as they come live.

  5. Weeks 10 to 12Response time and coverage evidenceProduct

    Against the week-4 baseline, plus the Action History compliance trail.

Consumer Insights

  1. Week 3Connect and configureSolution Architect

    Channels, open-web sources, sub-brands, competitor set, executive or spokesperson keywords.

  2. Week 3Wow moment: the category rankSolution Architect

    "You are #7 of 11 and here is who took the share." Nobody has shown them that number before.

  3. Weeks 4 to 8Themes, spikes and sub-brand spreadProduct

    Turn a spike into an explained event, and find the sub-brand quietly dragging the average.

  4. Weeks 8 to 12The board-ready numberProduct + SA

    Agree the single figure the CMO will quote, and the movement since kickoff.

AI Paid Media

  1. Week 3Connect and reconcileSolution Architect

    Ad accounts, GA4, MMP, offline conversions where the cycle needs it. Reconcile spend and conversions against their own platform before anyone sees a number.

  2. Week 3Goals enteredProduct + SA

    From the POC KPI sheet, at the agreed scope. This turns the Overview metrics table into performance against intent.

  3. Week 4Wow moment: the first real SignalSolution Architect

    A critical signal on their own account, at ad-group level, with the evidence and a recommended action. Usually something they had not caught.

  4. Weeks 5 to 8Morning-report habit switchedSolution Architect

    Their daily check moves to Overview. This is the adoption test that matters most.

  5. Weeks 8 to 12Efficiency and time-returned evidenceProduct

    Goal achievement rate plus hours per week returned.

Reporting

  1. Week 3Capture their formatSolution Architect

    If they are replacing an incumbent, get a copy of that report and match it before improving on it.

  2. Weeks 4 to 5Dashboards and saved reports builtSolution Architect

    Role-based splits where leadership and operators need different views.

  3. Week 5Wow moment: the report arrives without anyone building itSolution Architect

    Friday morning, in the inbox, matching their format. For several accounts this is the actual purchase.

  4. Weeks 6 to 12Confirm delivery, widen distributionProduct

    Check the run history rather than assuming. Add leadership to the recipient list.


Checkpoints

Day 30

Brand Brain signed off
Gate

Completed in weeks 1 to 2, not in progress. If it is not done, everything downstream is at risk.

Data reconciles
Gate

Our numbers match their platform. Do not add scope until this is true.

First wow moment landed
Must

At least one per module bought, and the customer has seen it.

Baselines captured
Must

Written and agreed. See goal setting.

More than the SPOC logged in
Watch

Access is organisation-wide. If only one person uses it, the rollout has not happened.

Blockers written down
Watch

With owners and dates, in the shared tracker.

Day 60

The old process stopped
Must

Not supplemented, stopped. The morning check, the reply queue, the manual report.

Weekly actives approaching seats
Must

Adoption is the phase-two job and the phase-two failure mode.

Movement on the primary goal
Must

Even partial. Direction matters more than magnitude at this point.

Scheduled deliveries confirmed
Watch

Someone has actually received the report, not just been sent it.

Feedback loop closed
Watch

Rejections and edits are changing rules, skills and playbooks.

Day-90 audience agreed
Plan

Who will be in the room, and what they need to see.

Day 90

Primary goal met, or missed for an understood reason
Decide

Against the original written criterion, in the customer words.

Usage sustained
Decide

Not a spike around review time.

An advocate other than the SPOC
Decide

Someone else will say it works, unprompted.

Commercial built from real volumes
Decide

Not an estimate. Use the pricing model and the scraping calculator.

Gaps disclosed by us first
Credibility

Volunteering what did not land is what makes the rest believable.

Decision: convert, extend, or stop
Outcome

An honest stop beats a drifting pilot.


Shared activities across all 13 weeks

A pilot where only Zocket has tasks is a pilot the customer is watching rather than running. Put this table in the pilot document.

ActivityCadenceOwnerCustomer
Weekly customer callWeeklyCS runs it, goals first. Product brings adoption numbersSPOC attends, decisions made in the call
All customer communicationContinuousCS, always. PM and SA route through CSNamed escalation contact
Onboarding trackerContinuousSA maintains status, PM owns the formatPrioritises and signs off
Product analytics dashboardWeeklyPM builds and reads it, CS acts on itn/a
Adoption interventionWeeklyProduct spots the dip, CS makes the callChases internal usage
Demos and trainingWeeks 2 to 8SA delivers, CS arrangesSends the right people
Feedback on outputContinuousSA feeds it into rules, skills, playbooksSays what was wrong and why
RequirementsMonths 1 and 2PM + SA coordinate and deliver, CS communicatesPrioritises
30 / 60 / 90 reviewAt each checkpointCS runs the room, Product brings the evidenceValidates against their own source

What kills pilots

In rough order of frequency
  1. No written success criterion. Everything else follows from this.
  2. Brand Brain not finished in weeks 1 to 2. Module work on a half-built graph produces output the client rejects, and the pilot never recovers the time.
  3. Numbers that do not reconcile. Fix before adding scope, always.
  4. Only the SPOC logs in. No advocate at day 90.
  5. Reporting configured but never delivered. Check the run history.
  6. Blockers carried silently. A gap disclosed early is a requirement. The same gap discovered by the customer at day 80 is a credibility problem.
  7. The economic buyer meets the product for the first time at day 90.
  8. Scope creep instead of depth. A second module while the first is unproven doubles the surface area and halves the evidence.

Adapting the shape

  • Enterprise and BFSI: add two to four weeks before week 1 for security review and access. Kotak Neo's own process is a two to three week evaluation across several team leads before pricing is discussed, so align to theirs rather than imposing ours.
  • Creative pilots: scope in masters and adaptations, and state in writing that iterations do not count against the cap. That is the live Lenovo structure and it removes the biggest unspoken fear.
  • ORM pilots: the shadow-mode week sits inside weeks 3 to 4 and is not negotiable.
  • Agency or multi-stakeholder: issue agency roles in week one. A pilot where the agency cannot log in stalls on the agency timeline rather than yours.